Minister Nurković visits whole motorway section, three bridges are fully completed and first segment of Moračica connected
Published on: Jul 11, 2019 • 4:00 PM Author: PR Service
Minister of Transport and Maritime Affairs Osman Nurković and his associates and representatives of the company China Road and Bridge Corporations (CRBC) visited the whole priority section of the Bar-Boljare motorway.
Minister Nurković expressed satisfaction with the volume of the preformed works, as well as expectation that the new deadline for the completion of the works, September 2020, will be respected.
Minister Nurković said that understanding of all participants and help to the contractor is necessary in order to finish this extremely complex project.
About 96% of works on the bridges construction or pillars and foundations have been completed, while about 54% of works on the superstructure have been completed. Superstructure was completed entirely on the three bridges: Gornja Mrka, Suvovar and Preslo, while one lane of the five bridges: Mištica, Uvač 1, Uvač 3, Pajkov Vir and Jabuka is completed. The degree of the works completion on the superstructure of the bridge Moračica is 80%. One segment of the superstructure is connected, while the overall bridge connection is expected by September this year.
From the total of 16 tunnels, 15 have been dug. There are 20m remaining in the right tunnel tube Mateševo. The construction of the upper part of the secondary coating has been almost finished, 94.7% of works have been completed until now.
The visit identified a few problems the contractor is facing on the field. It was agreed that all problems must be solved with the involvement of all stakeholders: Montenegro State Audit Institution, the control unit of the project Monteput, supervision and engineers of the CRBC.
The access roads in the length of 65 km were built in the previous period, alongside the motorway section, what is also one of the motorway construction benefits, Minister Nurković recalled.
All these works have had an impact on the environment; therefore Minister Nurković urged everyone to have an understanding of the possible effects, but also reminded that the contractor must protect the environment to the extent possible.