Please note: The page below represents the archived content relating to the previous Government of Montenegro. Some of the information might be inaccurate or outdated.
Archive

ADDENDUM 4

Published on: Jun 13, 2006 8:35 PM Author: Tenderi
Republic of Montenegro
Government of the Republic of Montenegro
DIRECTORATE FOR PUBLIC WORKS
Ref:05-1687/1
Podgorica, June 12 2006

In conformity with Article 18 og the Public Procurement Law hereby follows:

ADDENDUM 4

Tender Documents No. 05-25/06 for works on construction and commissioning of the Kindergarten - Podgorica, following questions received from the tenderers having purchased tender documents:

Heating-installations:
1. Heating units: it is not clear if the building needs to have total capacitz of 400 KW (together in two units), or two heating units each 400 KW (what means a total capacitz of 800 KW).
2. The hot water should be provided by electricity heating or to be produced with the cental heating unit (fired by oil).
3. Do we need unit prices for heating works

Sanitary works:
4. The quantities for the hydrant system is included in the quentities of cold water pipes, because there are no separatelz quantities for hydrant.
5. Are there some rainwater down pipes inside the building,or all rain watwr will be sewed outside of the building
6. The toilets are executed as standing object (not hanged on the wall)
7. The urinals are electronical (infrared) swiched or are to be swiched manually
8. Is there anz fad/grace-separator (or other separator) for the kitchen

Ventilation:

9. The ventilation cannels in the kitchen are to be fad-tide
10. Do we need unit prices for the ventilation works
11. The described ventilation machines for the laundry and the kitchen are only to bring in the air or they are also to bring out the air

Clarifications of questions hereby enclosed in form of the original documents furnished by respecive Deisgners.

Please be kind to confirm receipt of this Addendum.

Faithfully,

Zivkovic Zarko, CE
DIRECTOR



Re: Clarifications of the HVAC Final Design
Kindergarten and Nursery, Block V, Podgorica


Answers and clarifications of some concepts from the HVAC Final design - Kindergarten and Nursery, Block V, Podgorica will follow the original sequence of questions:

1. Heat capacity of 400 kW refers to one heating unit, hence the total heat consumption is Q = 2x400kW 800 kW.
2. Hot sanitary (consuming) water (60o) is provided by virtue of hot water from boilers (90/70oC) over winter, and by virtue of electrical heaters over summer when the boilers are out of function.
3. The Designer in Charge is not familiar with the equipment unit prices you dispose of.
9. Ducts in kitchen are used only for supply of fresh air, while the polluted air is exhausted separately.
10. The same as for Item 3.
11. The designed concept assumes supply of fresh air and exhaust of polluted air in/from the
kitchen and the laundry

Kind regards,

Rajko Jankovic, McE
HVAC Design
Designer in Charge


Re: Clarification Water and Sewage System
Kindergarten, Podgorica

Question 4 Clarification

Pipe quantities for hydrants are included in the cold water pipe quantities as summarized in the
Bill of Quantity

Question 5 Clarification

There are no rainwater drainage pipes in the building. There is only the external drainage of the rainwater.

Question 6 Clarification

The design envisages stand-alone toilet bowls.

Question 7 Clarification

The design envisages manual pissoirs

Question 7 Clarification

The design envisages grease separator

Faithfully,

Zahid Redzepagic CE

Podgorica June 08 2006
Is this page useful?